Commissioning of 42000 Air Separation Unit Exported to Indonesia Will be Conducted
May 19, 2020
The single machine commissioning, exposed cooling experiment and pearlite filling of our KDONAr-42000/42000/1200 ASU in Indonesia which is built for the OSS Stainless Steel Integrated Project with an annual output of 3 million tons, have been completed with the joint efforts and cooperation.
Also, the supporting Phase II power plant of this project will be combined to the grid on December 28, 2019, providing power to our equipment. The commissioning of this air separation unit is planned to be conducted in early January, and our commissioning personnel are on the way to the site to lead the trial production.